View Issue Details

IDProjectCategoryView StatusLast Update
0000603T99X171.00 SKB EagleHWpublic2019-06-24 16:44
Reporter(ALTech) SB ParkAssigned To(HW) Sean Chiang Due Date2019-04-12 11:33
PriorityimmediateSeveritys1-catastrophicReproducibilityN/A
Status closedResolutionfixed 
Summary0000603: [KC certification] Schedule of KC
DescriptionHi Sean
We discussed about KC certification. According to WBS, the schedule of KC is :
   1. Foxconn pre test with DVT : end of Apr ~ 5/13
   2. Delivery to KC Samples : 5/14~5/17
   3. ALT start KC certification : 5/20.
I want to pre test at Korea Lap(one tech) before KC certification. but this schedule is impossible.
I just want to pre test EMI RE/CE at Korea Lab before KC certificaiton. (not total EMC pre test but EMI RE/CE)

I ask to your favor.
1. could you give the some samples for EMI RE/CE earlier.
2. You'll give ALT to KC certificaion sample after finishing pre test.
    1) I worry that some test (ESD, Surge) will have a bad influence of samples
    2) These samples may have demages after ESD, surge test.
TagsNo tags attached.
Attach Tags

Users monitoring this issue

User List (ALTech) BY Lee , (ALTech) Eric Kim , (ALTech) Jewoo Lee , (ALTech) Juyoung Park , (ALTech) Philip , (ALTech) SH Son , (ALTech) SY Yoon , (HW) Catherine Chen , (HW) Jim Liang , (PM) Sheila Tu , (PM) Tiffanie Lai , (RD) Fu-chiang Young

Activities

(PM) Sheila Tu

2019-04-08 19:11

developer   ~0001906

Hi SB, I heard that ALT is planning to use 6pcs for KC certification before.
According to your questions, how many pcs that you were planning to use on your pre-test?

(ALTech) SB Park

2019-04-08 22:37

developer   ~0001913

Hi Sean, ALT is going to use 6pcs for KC Certification. and I'll have a pre-test "RE and CE" before KC.
If you give me 2 pcs first quickly, I can pre test.

(PM) Sheila Tu

2019-04-09 08:23

developer   ~0001917

Hi SB,
We will take 6pcs from ALT's quantity to proceed with pre-test and send them to you for your KC certification.
Do you mean that you want to keep 2 out of 6 pcs to proceed with your pre-test first?

(ALTech) SB Park

2019-04-09 08:44

developer   ~0001919

Hi Sheila
that's correct

(PM) Sheila Tu

2019-04-09 11:27

developer   ~0001920

Got it, will deliver 2 out of 6pcs with your quantity for your requirement.

(ALTech) SB Park

2019-04-22 13:49

developer   ~0002112

Hi Sheila, Sean
according to your Eagle project tracker 190417, the KC schedule is changed. as is version is 5/20~6/14, to be version is 5/22~6/14.
It is impossible to finish KC certification for 3 and 1/2 week. (besides there is a holiday in this period)
I asked Onetech to KC schedule. they said that it takes 6W for KC certification.
So. I am going to start KC ceritficatin at 08 May 2019.

(ALTech) SB Park

2019-04-23 09:02

developer   ~0002133

Hi Sheila, Sean
I'll start KC certificaiton at 08 May 2019.

I need some documents for KC certification :
  1. Schematic
  2. Component Location diagram
  3. block diagram (I already received block diagram at Jan 2019, I want to final version)

this document should be submit to certification Lab until 07 May

(PM) Sheila Tu

2019-04-23 11:43

developer   ~0002142

Hi SB, as the discussions during our previous weekly meeting, our company policy doesn't allow us to provide those kind of documents. And we also discussed that FXN will in charge of the communation with Onetech to solve this problem.
After you provide the application form to Onetech, please let us know the contact window of Oneteck. Thank you.

(ALTech) SB Park

2019-04-24 20:22

developer   ~0002180

Hi Sheila.
I will have a meeting with member of KC certification. after finishing this meeting. I'll give you to information about application form and contact point(mail address)

(ALTech) SB Park

2019-04-25 16:41

developer   ~0002203

Last edited: 2019-04-25 16:42

Hi Sheila

1. contact person : sueyong.lee@onetech.co.kr (onetact engineer)

2. the submitted docoment list
    1) Model name (ALT and Onetech use the model name BFX-AT100 and BFX-UH200. So all document should be used these model name)
    2) Component Location Diagram
    3) Block diagram
    4) Antenna specification (for BT antenna. see attached file)
    5) 8pin (RJ45) modular KC certification.
        - If you have a KC certification of J801 of EAGLE board. you submit this document
        - If not have a KC certification of J801 of EAGLE board.
          you can submit a header of Lan cables KC certification.
        - If you don't have kc certification of J801 and Header of Lan cables
          you submit the description information of J801 or Header of Lan cables
    6) address of manufacture's factory (Vietnam)

(ALTech) SB Park

2019-04-25 16:42

developer   ~0002204

Hi Sheila
see attached file (antenna specification)

(PM) Sheila Tu

2019-04-26 08:46

developer   ~0002210

Hi Sean, please help to assign our engineers to prepare the related design documents for KC. Thank you.

(ALTech) SB Park

2019-04-29 14:21

developer   ~0002255

Hi Sean
I have a question of clock frequecy
    1. Y401 : 24MHz (Amlogic)
    2. Y801 : 25MHz (PHY ic)
    3. Y1001 : 20MHz ( BT ic)
    4. DDR Clk : 1333MHz
Are they right?
Is there another clk frequency of Eagle board?

(ALTech) SB Park

2019-05-02 22:07

developer   ~0002362

Hi Sean
I had a meeting with onetech. the onetech manager request the document. please give him to documents.
and the clock frequency is right?
    1. Y401 : 24MHz (Amlogic)
     2. Y801 : 25MHz (PHY ic)
     3. Y1001 : 20MHz ( BT ic)
     4. DDR Clk : 1333MHz

(ALTech) SB Park

2019-05-03 13:55

developer   ~0002367

Hi Sean
I update EMI RE pre test result. It is pass.
1. test condition : 4K stream display using youtube. Insert USB memory stick, headset,
2. test case
    1) 30~1000MHz (Youtube play) : pass
    2) 1G~6GHz (Youtube play) : pass
    3) 30~1000MHz (usb stream play) : pass
    4) 1G~6GHz (usb stream play) : pass
    5) 1G~6GHz (BT) : pass
3. see attached file
1-6G_BT_AV.PDF (18,607 bytes)
1-6G_IP_AV.PDF (18,539 bytes)
1-6G_USB_AV.PDF (18,504 bytes)
30-1G_IP.PDF (18,297 bytes)
30-1G_USB.PDF (17,706 bytes)

(HW) Sean Chiang

2019-05-03 15:31

developer   ~0002370

Hi SB,
The frequency of crystals and DDR clock you provided are correct. Thanks.

(HW) Sean Chiang

2019-05-03 15:39

developer   ~0002371

Hi Jim and Catherine,
Please check SB's comment on 4/25 and 4/26 and prepare the doc in advance as below item2~5.
Sheila will bridge us with Onetech later. And please provide your doc. through another mail thread.

=====================================================
    2) Component Location Diagram
    3) Block diagram
    4) Antenna specification (for BT antenna. see attached file)
    5) 8pin (RJ45) modular KC certification.
        - If you have a KC certification of J801 of EAGLE board. you submit this document
        - If not have a KC certification of J801 of EAGLE board.
          you can submit a header of Lan cables KC certification.
        - If you don't have kc certification of J801 and Header of Lan cables
          you submit the description information of J801 or Header of Lan cables
================================================================

(HW) Sean Chiang

2019-05-14 19:41

developer   ~0002521

Hi SB,
May I know what's the test condition for RE/CE/EMS test in Onetech?
As per our discussion last time, we are ready to submit the EMC test but I would like to sync up with you and see if the test condition in your site is same with us.
Therefore, if you found any problem, we can ensure that we have the same test condition, environment and setup.

(ALTech) SB Park

2019-05-14 21:10

developer   ~0002524

Hi Sean.
 I don't know well the test condition at Onetech. because I don't join the all test of KC certi. If some tests has fail, I'll go there and check test condition. If test is pass, I just receive the result to Onetech manager.
If fail happens, I quickly check and inform to you.

Issue History

Date Modified Username Field Change
2019-04-04 10:47 (ALTech) SB Park New Issue
2019-04-04 10:47 (ALTech) SB Park Status new => assigned
2019-04-04 10:47 (ALTech) SB Park Assigned To => (HW) Sean Chiang
2019-04-04 10:47 (ALTech) SB Park Issue Monitored: (PM) Sheila Tu
2019-04-04 10:47 (ALTech) SB Park Issue Monitored: (PM) Tiffanie Lai
2019-04-04 10:48 (ALTech) SB Park Issue Monitored: (ALTech) SY Yoon
2019-04-04 10:48 (ALTech) SB Park Issue Monitored: (ALTech) Philip
2019-04-04 10:48 (ALTech) SB Park Issue Monitored: (ALTech) Jewoo Lee
2019-04-04 10:48 (ALTech) SB Park Issue Monitored: (ALTech) Eric Kim
2019-04-04 10:48 (ALTech) SB Park Description Updated
2019-04-08 19:11 (PM) Sheila Tu Note Added: 0001906
2019-04-08 22:37 (ALTech) SB Park Note Added: 0001913
2019-04-09 08:23 (PM) Sheila Tu Note Added: 0001917
2019-04-09 08:44 (ALTech) SB Park Note Added: 0001919
2019-04-09 11:27 (PM) Sheila Tu Note Added: 0001920
2019-04-22 13:49 (ALTech) SB Park Note Added: 0002112
2019-04-22 13:49 (ALTech) SB Park Issue Monitored: (ALTech) BY Lee
2019-04-23 09:02 (ALTech) SB Park Note Added: 0002133
2019-04-23 11:43 (PM) Sheila Tu Note Added: 0002142
2019-04-24 20:22 (ALTech) SB Park Note Added: 0002180
2019-04-25 16:41 (ALTech) SB Park Note Added: 0002203
2019-04-25 16:42 (ALTech) SB Park Note Edited: 0002203
2019-04-25 16:42 (ALTech) SB Park File Added: BT_antenna_specification.pdf
2019-04-25 16:42 (ALTech) SB Park Note Added: 0002204
2019-04-26 08:46 (PM) Sheila Tu Note Added: 0002210
2019-04-29 14:21 (ALTech) SB Park Note Added: 0002255
2019-04-29 16:31 (ALTech) SB Park Issue Monitored: (ALTech) Juyoung Park
2019-05-02 22:07 (ALTech) SB Park Note Added: 0002362
2019-05-03 13:55 (ALTech) SB Park File Added: 1-6G_BT_AV.PDF
2019-05-03 13:55 (ALTech) SB Park File Added: 1-6G_IP_AV.PDF
2019-05-03 13:55 (ALTech) SB Park File Added: 1-6G_USB_AV.PDF
2019-05-03 13:55 (ALTech) SB Park File Added: 30-1G_IP.PDF
2019-05-03 13:55 (ALTech) SB Park File Added: 30-1G_USB.PDF
2019-05-03 13:55 (ALTech) SB Park Note Added: 0002367
2019-05-03 15:10 (HW) Sean Chiang Issue Monitored: (RD) Fu-chiang Young
2019-05-03 15:10 (HW) Sean Chiang Issue Monitored: (HW) Jim Liang
2019-05-03 15:18 (HW) Sean Chiang Issue Monitored: (HW) Catherine Chen
2019-05-03 15:31 (HW) Sean Chiang Note Added: 0002370
2019-05-03 15:39 (HW) Sean Chiang Note Added: 0002371
2019-05-14 19:41 (HW) Sean Chiang Note Added: 0002521
2019-05-14 21:10 (ALTech) SB Park Note Added: 0002524
2019-05-30 11:12 (ALTech) SB Park Issue Monitored: (ALTech) SH Son
2019-06-24 16:44 (ALTech) SB Park Status assigned => closed
2019-06-24 16:44 (ALTech) SB Park Resolution open => fixed